Our newest data center, located in South Carolina.
50 MW
via Existing Substation
50 MW
via On-Site Gas Microgrid
200 MW
via New Substation
650 MW
via Utility Gas Powerplant
Power & Delivery Timeline
230 kV transmission and natural gas lines on-site
50 MW via existing substation
50 MW via onsite gas microgrid
200 MW via new substation
650 MW via utility gas power plant
Property
Class A industrial park spanning 868 acres with 250 acres available for development.
230 kV transmission and natural gas lines on-site
4MPOE, 288ct dark fiber, ample water
90% completed for Phase 1A & B
Lot Overview
One single-story building, one two-story building, and an outside natural gas microgrid (50 MW capacity)
Powering phase 2
One two-story building
Six two-story buildings
*This assumes construction of the Phase 1A & B building structure begins in August 2025. Delays in tenant acquisition could postpone construction commencement to February 2026 or later, Impacting the overall dellvery schedule.
We're positioned within the thriving Atlanta-Greenville-Charlotte-Raleigh Economic Corridor placing us within close proximity to major cities and sea cables.
Located within an industrial park, equipped with an existing substation, 230kV transmission line, and natural gas line for future expansion.
Phase 1 (100 MW) is targeted for delivery in Q2 2026.
Clearly defined roadmap scaling from 100 MW to 950 MW across three phases: short, medium, and long-term.
Design & MEP firm leading the Construction Documentation phase for March 2025 completion.
Delivering preconstruction services, committed to full construction.
Partnered for critical facility management services.
Over $40 billion in combined executive deal value.
AI-Optimized Hardware
Scalability on Demand
Our data centers are located in key technological hubs, ensuring minimal latency for AI operations, faster data transfers, and improved user experiences across the globe.
Phase 1 (100 MW) is targeted for delivery in Q2 2026.
50 MW via an existing substation with distribution handled by the utility
50 MW via an on-site natural gas microgrid; sufficient gas supply is confirmed
Project delivery target
Submitted, civil work is underway as of March 2025
90% complete, completion expected by March 2025
Anticipated by April 2025
Secured, gensets scheduled for Q3 2025