Project Spero

950 MW.

Our newest data center, located in South Carolina.

50 MW

via Existing Substation

50 MW

via On-Site Gas Microgrid

200 MW

via New Substation

650 MW

via Utility Gas Powerplant

project spero conceptual site plan

Power & Delivery Timeline

Infrastructure

230 kV transmission and natural gas lines on-site

Phase 1A (12-18 mos)*

50 MW via existing substation

Phase 1B (12-18 mos)*

50 MW via onsite gas microgrid

Phase 2 (24-36 mos)

200 MW via new substation

Phase 3 (48-60 mos)

650 MW via utility gas power plant

Property

Summary

Class A industrial park spanning 868 acres with 250 acres available for development.

Size

230 kV transmission and natural gas lines on-site

Utilities

4MPOE, 288ct dark fiber, ample water

Design

90% completed for Phase 1A & B

Lot Overview

(8) (200 MW) Phase 1A&B, Phase 2

One single-story building, one two-story building, and an outside natural gas microgrid (50 MW capacity)

(7) New Substation

Powering phase 2

(9) (100 MW) Phase 2

One two-story building

(10) (650 MW) Phase 3

Six two-story buildings

*This assumes construction of the Phase 1A & B building structure begins in August 2025. Delays in tenant acquisition could postpone construction commencement to February 2026 or later, Impacting the overall dellvery schedule.

TigerDC data center entrance image

Features

Strategic Location

We're positioned within the thriving Atlanta-Greenville-Charlotte-Raleigh Economic Corridor placing us within close proximity to major cities and sea cables.

Robust Infrastructure

Located within an industrial park, equipped with an existing substation, 230kV transmission line, and natural gas line for future expansion.

Timely Delivery

Phase 1 (100 MW) is targeted for delivery in Q2 2026.

Phased Growth

Clearly defined roadmap scaling from 100 MW to 950 MW across three phases: short, medium, and long-term.

A World-Class Team

AlfaTech

Design & MEP firm leading the Construction Documentation phase for March 2025 completion.

Holder Construction

Delivering preconstruction services, committed to full construction.

T5 Data Centers

Partnered for critical facility management services.

Transaction Experience

Over $40 billion in combined executive deal value.

temporary image

Data Center Highlights

AI-Optimized Hardware

    Latest GPUs, TPUs, and specialized AI chips
    Tailored for deep learning and machine learning applications
    Accelerated training and inference speeds

Scalability on Demand

    Seamless data access with low latency
    Effortless resource provisioning

Strategic Placement for Low Latency

Our data centers are located in key technological hubs, ensuring minimal latency for AI operations, faster data transfers, and improved user experiences across the globe.

data center locations map

Timely Delivery

Phase 1 (100 MW) is targeted for delivery in Q2 2026.

Phase 1A

50 MW via an existing substation with distribution handled by the utility

Phase 1B

50 MW via an on-site natural gas microgrid; sufficient gas supply is confirmed

Q2 2026

Project delivery target

Mass Grading Permit

Submitted, civil work is underway as of March 2025

Phase 1 Design

90% complete, completion expected by March 2025

Construction Permit

Anticipated by April 2025

Critical long-lead items

Secured, gensets scheduled for Q3 2025